A hard look at the queue-reform ripple effects: campuses previously heading to Loudoun are quietly re-siting to West Virginia and Ohio. Here is the pattern in the data.
In Short
- Loudoun, VA — saturated
- WV — three new 500 MW campuses
- OH — two hyperscaler campuses
The queue reform in one paragraph
FERC Order 2023 took effect in 2026, moving PJM from a serial-study queue to a cluster-study model.
Where the traffic went
Loudoun, VA — saturated
WV — three new 500 MW campuses
OH — two hyperscaler campuses